Cut & Fill Calculator — ft, yd³ (Slope Grading)

Dimensions in feet · Volumes in yd³ · Swell factor, hauling & trucks
Survey geometry + explicit volume-state factors

How to use this calculator

Pick the survey shortcut that matches your data. Simple — one uniform cut or fill depth across a rectangle (driveway lift, lawn re-grade, shed pad). Two-Point — sloped existing vs sloped finish grade along a length (driveway with crown, walkout basement strip). Grid — four corner spot elevations averaged with the end-area method for an irregular pad. The result drives haul-off trucks, import quantity, and whether you balance on site or pay for off-haul.

Swell converts bank cut to loose excavated volume. Compaction shrink converts compacted fill demand to loose import volume. Enter project/material factors and truck capacity explicitly; soil labels below are reference presets only.

Sand/Gravel 15% Topsoil/Loam 25% Clay 35% Shale 40% Rock 50%
Method & Dimensions
Driveway lift 50×12, 6" fill Building pad 40×30, 1 ft cut Garage pad 24×24, 6" cut Patio level 12×16, 4" cut Lawn regrade 30×40, 6" fill Drainage swale 100×4, 1 ft cut Walkout basement 30×8, 4 ft cut
ft in
ft in
Positive = cut (remove soil) · Negative = fill (add soil)
ft in
Soil expands when excavated. Sand ~15% · Loam ~25% · Clay ~35% · Rock ~50%
%
Loose imported fill loses volume when rolled to 95% Proctor. Order more loose yards than the finished hole.
%
loose yd³/load
Payload weight can govern before bed volume; verify with the hauler.
Diagram · tap labels to focus inputs
Plan View
Results
Earthwork Volumes
Cut Volume (bank)
yd³
Fill Demand (compacted)
CCY
Net Earthwork
yd³ cut
Excavated Cut (loose)
LCY
Area
ft²
Cut Haul Loads by Volume
loads

Saved Calculations

TimeMethodArea ft²Cut yd³Fill yd³Net yd³Haul yd³Trucks
No saved calculations

How to Calculate Cut & Fill Volumes

Pick the method that matches your survey data. Simple applies one uniform cut or fill depth over a rectangular pad — handy for a driveway lift or a building pad strip. Two-Point compares existing grade against finished grade along a length and automatically splits the prism at the crossover where cut turns to fill. Grid averages four corner spot elevations, the field shortcut for the average-end-area method. Bank (in-place) volumes are reported separately for cut and fill so you can plan balanced earthwork before ordering haul-off or import.

Formulas

Simple: volume = plan area × signed depth. Two-point: the linear depth-difference prism is integrated and split at its zero crossing. Four-corner grid: the rectangle is divided along the NW–SE diagonal into two linear triangles; positive and negative portions are integrated separately so cut and fill do not cancel. Cut is reported as bank cubic yards (BCY); fill demand is compacted cubic yards (CCY).

Loose excavated cut = BCY cut × (1 + entered swell). Loose import = CCY fill / (1 − entered compaction shrink). Loads by volume = ceil(LCY / entered loose yd³ per load). Payload weight, reuse suitability, moisture, stripping, overexcavation and haul routing require separate project inputs.

Swell & Shrink Factors

Excavated soil bulks up: sand/gravel 10–20%, loam/topsoil 20–30%, clay 30–40%, shale 35–45%, rock 40–60%. Compacted structural fill shrinks 10–20% from bank volume, so imported fill is usually under-estimated if you ignore compaction — confirm import quantities with the fill & backfill calculator. For trench grading, add over-dig per the OSHA Type C slope and a 5–10% waste allowance.

Where this fits on site

Use this tool for the rough mass-haul balance, then size the dig with the excavation volume & cost calculator. Surplus cut hauled off or aggregate brought in is priced by the ton with the gravel & aggregate calculator, and any stripped topsoil to respread is tracked in the topsoil & mulch calculator. Once subgrade is set, pads carry into the concrete slab calculator.

On the jobsite

Three numbers move earthwork bids in 2025 USA. Haul-off runs $12–25 per loose yd³ within 20 miles of a dump; tipping fees add $8–18/ton. Imported structural fill trucked in is $18–35/ton delivered, and you need 10–20% more loose than the finished hole because of compaction — the row above sizes that order. The #1 estimator miss on residential cut & fill: forgetting the topsoil strip (typically 4–6″ off the whole footprint, hauled or stockpiled) before counting the structural cut underneath. OSHA 29 CFR 1926 Subpart P sets the trench / cut slope (Type C soil = 1½H:1V) — add that over-dig to anything deeper than 4 ft before pricing the haul.

FAQ

Bank vs loose volume? Bank is undisturbed in-place soil — what you pay an earthwork sub to excavate. Loose is the bulked-up volume on trucks after excavation, which is what sizes haul-off. Why is net not zero on a balanced site? Bank cut equals bank fill at balance, but loose haul still moves; the swell factor only scales hauling, not the bank quantities. How many trucks? Based on a standard 10 yd³ tandem dump on loose material — lower the divisor mentally for a 12 yd³ truck or articulated hauler.

Calculation notesWhat this calculator doesOpen the formula basis, references and assumptions when you need to verify the detailed method.Review details

Entered areas, elevations or average depths are used to estimate cut, fill and net balance volumes with user-selected bulking factors.

Reference context

  • geometric volume relationships
  • project geotechnical information
  • supplier density and compaction data

Important assumptions

  • Dimensions, quantities and prices entered by the user are correct.
  • Waste, laps, overlaps, compaction and delivery allowances must match the actual project.
  • Results are preliminary takeoff estimates, not a sealed structural design or permit approval.

Quality notes updated: August 1, 2026. The repository includes per-page checks for browser errors, populated results, metadata, US-market visibility, duplicate IDs and shared quality controls.

Reference names describe the applicable design and product context; they do not replace a project-specific code review. Local codes, drawings, specifications and manufacturer instructions govern the final work. Report a calculation or interface issue.

Misha Noyr, M.Eng.

Misha Noyr, M.Eng.

Civil Engineer · 15+ yrs · structural design and geotechnics. Full bio →